🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 201

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 201 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Ramos
Gas
131 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Onshore wind project Y3-031, Tyrrell County
Onshore wind
131 MWWithdrawn / abandoned Tyrrell, NCPJM Feb 2013target 2016
Sunshine Solar
Solar · Sunshine Energy LLC
131 MWWithdrawn / abandoned ERCOT Sep 2022target 2026
Solar project IC-584, Treutlen County
Solar
131 MWWithdrawn / abandoned Treutlen, GASoutheast Jan 2017
NY Interconnection 3
Battery storage · NY Interconnection LLC
130 MWWithdrawn / abandoned New York, NYNYISO Sep 2021
Onshore wind project GEN-2007-026, Deaf Smith County
Onshore wind
130 MWWithdrawn / abandoned Deaf Smith, TXSPP May 2007target 2009
Battery storage project IC-1186, Clarke County
Battery storage
130 MWWithdrawn / abandoned Clarke, GASoutheast Oct 2023target 2027
Solar + storage project 25-IC-1359, Pearl River County
Solar + storage
130 MWWithdrawn / abandoned Pearl River, MSSoutheast Apr 2025
Solar project 962640, Stokes County
Solar
130 MWWithdrawn / abandoned Stokes, NCSoutheast Sep 2024
Solar project GI-2010-10, Alamosa County
Solar
130 MWWithdrawn / abandoned Alamosa, COWest Jul 2010target 2014
Solar project GEN-2024-315, Haskell County
Solar
130 MWWithdrawn / abandoned Haskell, OKSPP Mar 2025target 2029
Onshore wind project GEN-2002-015, Custer County
Onshore wind
130 MWWithdrawn / abandoned Custer, OKSPP Sep 2002
Crane Brook Solar Project, LLC
Solar · Crane Brook Solar Project
130 MWWithdrawn / abandoned Cayuga, NYNYISO Jun 2021
Gas project AA2-051, Philadelphia County
Gas
130 MWWithdrawn / abandoned Philadelphia, PAPJM Feb 2015target 2018
Solar project J3376, Mississippi County
Solar
130 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Onshore wind project GI-0001, Steele County
Onshore wind
130 MWWithdrawn / abandoned Steele, NDWest Apr 2000
Solar + storage project GEN-2023-066, Stanley County
Solar + storage
130 MWWithdrawn / abandoned Stanley, SDSPP Oct 2023target 2028
Solar project J2560, Sunflower County
Solar
130 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2022target 2027
Onshore wind project G0325, Grant County
Onshore wind
130 MWWithdrawn / abandoned Grant, WAWest Apr 2008target 2011
Solar project IC-692, Decatur County
Solar
130 MWWithdrawn / abandoned Decatur, GASoutheast Apr 2018
Onshore wind project U1-051, Clearfield County
Onshore wind
130 MWWithdrawn / abandoned Clearfield, PAPJM Mar 2008target 2011
Redding Tech West
Gas · Redding Tech West
130 MWWithdrawn / abandoned Ector, TXERCOT Aug 2021target 2024
Solar + storage project AF2-397, Fluvanna County
Solar + storage · Kidds Store II, LLC
130 MWWithdrawn / abandoned Fluvanna, VAPJM Apr 2020target 2023
Battery storage project GEN-2024-174, Mercer County
Battery storage
130 MWWithdrawn / abandoned Mercer, NDSPP Mar 2025target 2028
Mulberry Energy Storage
Battery storage · Mulberry Energy Storage 1, LLC
130 MWWithdrawn / abandoned Saratoga, NYNYISO Sep 2022
Mainesburg ESS
Battery storage · Juno Power Management LLC
130 MWWithdrawn / abandoned Tioga, PANYISO Jun 2020
Solar + storage project AH1-613, City Of Suffolk County
Solar + storage
130 MWWithdrawn / abandoned City Of Suffolk, VAPJM Sep 2021target 2025
Solar project J1036, Cottonwood County
Solar
130 MWWithdrawn / abandoned Cottonwood, MNMISO Mar 2018target 2020
NY115 - Newport Solar
Solar · Newport Deerfield Solar LLC
130 MWWithdrawn / abandoned Oneida, NYNYISO May 2021
Solar project AH1-386, Mecklenburg County
Solar
130 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2021target 2025
NY115 - Newport Solar
Solar · Newport Deerfield Solar
130 MWWithdrawn / abandoned Oneida, NYNYISO Feb 2023
Palmdale Energy
Gas
130 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2015target 2022
Solar + storage project J2688, Newton County
Solar + storage
130 MWWithdrawn / abandoned Newton, TXMISO Sep 2022target 2026
OCI SunShiner Solar
Solar · OCI SunShiner LLC
130 MWWithdrawn / abandoned Zavala, TXERCOT Feb 2023target 2026
Solar project AH1-237, Caroline County
Solar
130 MWWithdrawn / abandoned Caroline, VAPJM Sep 2021target 2024
Mulberry Energy Storage
Battery storage · Mulberry Energy Storage 1, LLC
130 MWWithdrawn / abandoned Saratoga, NYNYISO Sep 2024
Onshore wind project S54, Tazewell County
Onshore wind
130 MWWithdrawn / abandoned Tazewell, VAPJM Jun 2007target 2009
West Babylon
Battery storage · 174 Power Global Properties
130 MWWithdrawn / abandoned Nassau, NYNYISO Mar 2022
Onshore wind project GEN-2017-118, Cloud County
Onshore wind
130 MWWithdrawn / abandoned Cloud, KSSPP Nov 2017target 2024
Little Alligator Windfarm
Onshore wind
130 MWWithdrawn / abandoned Tyrrell, NCPJM May 2015target 2020
Solar + storage project J3226, Marshall County
Solar + storage
130 MWWithdrawn / abandoned Marshall, INMISO Sep 2022target 2026
Battery storage project C3-174, Salt Lake County
Battery storage
130 MWWithdrawn / abandoned Salt Lake, UTWest May 2023target 2028
Onshore wind project J2466, Howard County
Onshore wind
130 MWWithdrawn / abandoned Howard, IAMISO Sep 2022target 2027
Wild Ox Solar
Solar + storage · Wild Ox Solar Project, LLC
130 MWWithdrawn / abandoned Yates, NYNYISO Aug 2024
Solar project GEN-2018-088, Bowie County
Solar
130 MWWithdrawn / abandoned Bowie, TXSPP Nov 2018target 2027
Battery storage project J2646, Lincoln Parish County
Battery storage
130 MWWithdrawn / abandoned Lincoln Parish, LAMISO Sep 2022target 2026
Solar + storage project 1189, Converse County
Solar + storage
130 MWWithdrawn / abandoned Converse, WYWest Nov 2019target 2022
Milagro Wind
Onshore wind
130 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2011
Solar project W1-051, Franklin County
Solar
130 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2012
Moose Creek 1
Battery storage · Emeren US, LLC
130 MWWithdrawn / abandoned Lewis, NYNYISO Dec 2023
Page 201 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)