United States βΊ Grid βΊ Interconnection queues βΊ Georgia
BATTERY STORAGE Β· SOUTHEASTBattery storage project IC-1186, Clarke County
Battery storage project IC-1186, Clarke County is a 130 MW battery storage request withdrawn in the Southeast interconnection queue, in Clarke County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedMay 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-1186
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Athena DS Substation 115 kV Bus
- Location
- Clarke County, Georgia
- Technology
- Battery: 130 MW
- Total requested
- 130 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 26 October 2023
- Proposed online date
- November 2027
- Withdrawn
- May 2024
Location
Marker shows the centre of Clarke County; the queue data does not give exact sites.
Other requests in Clarke County
- Fall Line Hydro (aka Tallasee Shoals)Hydro Β· 4.0 MW Β· built
- Gas project IC-015, Clarke CountyGas Β· 620 MW Β· withdrawn
- Gas project IC-014, Clarke CountyGas Β· 620 MW Β· withdrawn
- Gas project IC-016, Clarke CountyGas Β· 620 MW Β· withdrawn
- Gas project IC-077, Clarke CountyGas Β· 564 MW Β· withdrawn
- Gas project IC-131, Clarke CountyGas Β· 564 MW Β· withdrawn
- Gas project IC-035, Clarke CountyGas Β· 185 MW Β· withdrawn
- Gas project IC-034, Clarke CountyGas Β· 185 MW Β· withdrawn
- Battery storage project IC-1181, Clarke CountyBattery storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem