United States › Grid › Interconnection queues › Georgia

HYDRO · SOUTHEAST

Fall Line Hydro (aka Tallasee Shoals)

Fall Line Hydro (aka Tallasee Shoals) is a 4.0 MW hydro request built and operating in the Southeast interconnection queue, in Clarke-Jackson Co County, Georgia, connecting to Georgia Transmission.

Queue statusOperating
  1. PlanningQueued Dec 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-032
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Tallasee Shoals 46 kV Sub
Location
Clarke-Jackson Co County, Georgia
Technology
Hydro: 4.0 MW
Total requested
4.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
31 December 2023

Location

Marker shows the centre of Clarke-Jackson Co County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Clarke-Jackson Co County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem