BATTERY STORAGE Β· NYISO

Moose Creek 1

Moose Creek 1 is a 130 MW battery storage request withdrawn in the NYISO interconnection queue, in Lewis County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1650
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Emeren US, LLC
Connection point (POI)
Boonville Substation 115 kV
Location
Lewis County, New York
Technology
Battery: 130 MW
Total requested
130 MW
Queue status
Withdrawn
Entered queue
12 December 2023

Location

Marker shows the centre of Lewis County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Lewis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem