United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOAntelope Energy Storage Center
Antelope Energy Storage Center is a 500 MW battery storage request withdrawn in the NYISO interconnection queue, in Lewis County, New York, connecting to NYPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1654
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Hydrostor USA Holdings, Inc , a subsidiary of Hydrostor Inc
- Connection point (POI)
- Adirondack 345kV substation
- Location
- Lewis County, New York
- Technology
- Battery: 500 MW
- Total requested
- 500 MW
- Queue status
- Withdrawn
- Entered queue
- 21 December 2023
Location
Marker shows the centre of Lewis County; the queue data does not give exact sites.
Other requests in Lewis County
- Sugar Maple SolarSolar · 125 MW · in study
- Flat Rock Wind PowerOnshore wind · 321 MW · built
- Flat Rock Wind PowerOnshore wind · 321 MW · built
- Number 3 Wind EnergyOnshore wind · 104 MW · built
- Number 3 Wind EnergyOnshore wind · 104 MW · built
- Copenhagen WindOnshore wind · 79.9 MW · built
- Copenhagen WindOnshore wind · 79.9 MW · built
- Roaring Brook WindOnshore wind · 79.7 MW · built
- Roaring Brook WindOnshore wind · 79.7 MW · built
- Chinook Energy Storage CenterBattery storage · 500 MW · withdrawn
- Chinook Energy Storage CenterBattery storage · 500 MW · withdrawn
- Antelope Energy Storage CenterBattery storage · 500 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem