United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

SOLAR Β· WEST

Solar project GI-2010-10, Alamosa County

Solar project GI-2010-10, Alamosa County is a 130 MW solar request withdrawn in the West interconnection queue, in Alamosa County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2010 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2010-10
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
San Luis Substation
Location
Alamosa County, Colorado
Technology
Solar: 130 MW
Total requested
130 MW
Service type
NRIS and ERIS
Study phase
Feasibility Study underway Request Withdrawn 6/15/12
Queue status
Withdrawn
Entered queue
27 July 2010
Proposed online date
October 2014
Withdrawn
June 2012

Location

Marker shows the centre of Alamosa County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Alamosa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem