πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

SOLAR Β· WEST

Solar project GI-2016-9, Alamosa County

Solar project GI-2016-9, Alamosa County is a 480 MW solar request withdrawn in the West interconnection queue, in Alamosa County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedJan 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2016-9
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
San Luis Substation 230 kV
Location
Alamosa County, Colorado
Technology
Solar: 480 MW
Total requested
480 MW
Service type
NRIS and ERIS
Study phase
Feasibility Study Complete System Impact Study Complete Facility Study Complete LGIA Negotiations Underway Request Withd
Queue status
Withdrawn
Entered queue
29 April 2016
Proposed online date
February 2023
Withdrawn
January 2020

Location

Marker shows the centre of Alamosa County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Alamosa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem