Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 20 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J3402, Juneau County
Battery storage
200 MWIn study Juneau, WIMISO Apr 2024target 2028
Battery storage project GEN-2024-327, Ward County
Battery storage
200 MWIn study Ward, NDSPP Mar 2025target 2028
Battery storage project J2532, Sangamon County
Battery storage
200 MWIn study Sangamon, ILMISO Sep 2022target 2026
Battery storage project AI1-023, Mclean County
Battery storage
200 MWIn study Mclean, ILPJM Apr 2022target 2026
Surplus; J1562
Battery storage
200 MWIn study Mississippi, ARMISO Jun 2025target 2027
Battery storage project GEN-2024-175, Greene County
Battery storage
200 MWIn study Greene, MOSPP Mar 2025target 2028
Battery storage project J2545, Buchanan County
Battery storage
200 MWIn study Buchanan, IAMISO Sep 2022target 2026
Battery storage project 21-100, Washington County
Battery storage
200 MWAgreement signed Washington, ORWest May 2021target 2028
Battery storage project J4137, Pulaski County
Battery storage
200 MWIn study Pulaski, ILMISO Sep 2025target 2030
Battery storage project GEN-2021-040, Cass County
Battery storage
200 MWIn study Cass, NESPP Apr 2021target 2029
Battery storage project GEN-2021-038, Titus County
Battery storage
200 MWIn study Titus, TXSPP Apr 2021target 2028
Battery storage project 103, Skagit County
Battery storage
200 MWPaused / redesign Skagit, WAWest Apr 2021target 2028
Battery storage project J3873, Gibson County
Battery storage
200 MWIn study Gibson, INMISO Dec 2024target 2029
Highbush Energy Storage
Battery storage · Hanwha Q CELLS USA Corp.
200 MWIn study Dutchess, NYNYISO Aug 2024target 2027
Battery storage project 633, Jerome County
Battery storage · NextEra Energy Resources Interconnection Holdings, LLC
200 MWAgreement signed Jerome, IDWest Jan 2022target 2027
Kresge Land Battery Storage
Battery storage · Kresge Land Battery Storage LLC
200 MWIn study Galveston, TXERCOT Mar 2025target 2027
Wheelhouse Energy Storage
Battery storage · NEER Interconnection Holdings, LLC
200 MWIn study Schoharie, NYNYISO Sep 2024target 2030
Battery storage project J2684, St. Clair County
Battery storage
200 MWIn study St. Clair, MIMISO Sep 2022target 2025
Battery storage project J3947, Shelby County
Battery storage
200 MWIn study Shelby, ILMISO Mar 2025target 2030
Battery storage project AG2-544, Mchenry County
Battery storage · Monarch Grid, LLC
200 MWIn study Mchenry, ILPJM Mar 2025target 2024
Battery storage project 514, Dekalb County
Battery storage
200 MWAgreement signed Dekalb, ALSoutheast Aug 2022target 2028
Battery storage project J3249, Vanderburgh County
Battery storage
200 MWIn study Vanderburgh, INMISO Apr 2024target 2028
Battery storage project 60, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Aug 2018target 2028
Surplus; J1588
Battery storage
200 MWIn study Cass, NDMISO Mar 2025target 2028
Battery storage project PIS011, Klamath County
Battery storage · PacifiCorp
200 MWIn study Klamath, ORWest Jun 2022target 2026
Battery storage project C3-011, Lake County
Battery storage · PacifiCorp
200 MWPaused / redesign Lake, ORWest Apr 2023target 2029
Battery storage project Company QH, White Pine County
Battery storage
200 MWIn study White Pine, NVWest Sep 2023target 2026
Battery storage project C2-04, Klamath County
Battery storage · PacifiCorp
200 MWIn study Klamath, ORWest Apr 2022target 2026
Battery storage project 898997, Rutherford County
Battery storage
200 MWIn study Rutherford, NCSoutheast Jun 2023
Battery storage project C3-171, Weber County
Battery storage
200 MWIn study Weber, UTWest May 2023target 2026
Battery storage project C3-008, Crook County
Battery storage · PacifiCorp
200 MWIn study Crook, ORWest Apr 2023target 2029
Battery storage project 898999, Robeson County
Battery storage · Masked
200 MWAgreement signed Robeson, NCSoutheast Jun 2023
Battery storage project J3515, Sangamon County
Battery storage
200 MWIn study Sangamon, ILMISO Apr 2024target 2026
Battery storage project PIS096, Lake County
Battery storage · PacifiCorp
200 MWIn study Lake, ORWest Nov 2024target 2028
Battery storage project PIS097, Crook County
Battery storage · PacifiCorp
200 MWIn study Crook, ORWest Nov 2024target 2028
Battery storage project J3480, Allegan County
Battery storage
200 MWIn study Allegan, MIMISO Apr 2024target 2026
Battery storage project GEN-2024-260, Buchanan County
Battery storage
200 MWIn study Buchanan, MOSPP Mar 2025target 2029
Battery storage project GEN-2024-092, Roosevelt County
Battery storage
200 MWIn study Roosevelt, NMSPP Oct 2024target 2029
Battery storage project GEN-2024-246, Eddy County
Battery storage
199 MWIn study Eddy, NMSPP Mar 2025target 2029
Overlook Storage
Battery storage · Origis Development LLC
199 MWIn study Dutchess, NYNYISO Oct 2024target 2028
Battery storage project PIS088, Salt Lake County
Battery storage
199 MWIn study Salt Lake, UTWest Sep 2024target 2028
Battery storage project GEN-2024-189, Ford County
Battery storage
199 MWIn study Ford, KSSPP Mar 2025target 2028
Battery storage project C2-109, Utah County
Battery storage
199 MWIn study Utah, UTWest May 2022target 2025
Battery storage project C2-110, Utah County
Battery storage
199 MWIn study Utah, UTWest May 2022target 2025
Battery storage project GEN-2024-355, Lubbock County
Battery storage
199 MWIn study Lubbock, TXSPP Mar 2025target 2030
Battery storage project GEN-2024-120, Oklahoma County
Battery storage
199 MWIn study Oklahoma, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-352, Jackson County
Battery storage
199 MWIn study Jackson, MOSPP Mar 2025target 2030
Battery storage project GEN-2024-177, Bossier Parish County
Battery storage
199 MWIn study Bossier Parish, LASPP Mar 2025target 2029
Battery storage project GEN-2024-164, Murray County
Battery storage
199 MWIn study Murray, OKSPP Mar 2025target 2030
Battery storage project 977397, Onslow County
Battery storage
199 MWIn study Onslow, NCSoutheast Jun 2025
Page 20 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)