BATTERY STORAGE · WEST

Battery storage project PIS096, Lake County

Battery storage project PIS096, Lake County is a 200 MW battery storage request in interconnection study in the West interconnection queue, in Lake County, Oregon, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued Nov 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
PIS096
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp
Connection point (POI)
Summer Lake substation
Location
Lake County, Oregon
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
27 November 2024
Proposed online date
December 2028

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem