BATTERY STORAGE · MISO

Battery storage project J2684, St. Clair County

Battery storage project J2684, St. Clair County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in St. Clair County, Michigan.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2684
Grid region
MISO (Midcontinent)
Connection point (POI)
BUNCE
Location
St. Clair County, Michigan
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
8 September 2022
Proposed online date
January 2025

Location

Marker shows the centre of St. Clair County; the queue data does not give exact sites.