Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project Q39, Kern County Solar |
396 MW | Withdrawn / abandoned |
| Desert Butte Solar Farm Solar |
387 MW | Withdrawn / abandoned |
| Gas project 419, Cowlitz County Gas |
375 MW | Withdrawn / abandoned |
| Guadalupe II Gas ยท Calpine |
362 MW | Withdrawn / abandoned |
| Gas project Y2-103, Lake County Gas |
360 MW | Withdrawn / abandoned |
| Nuclear project Y1-005, Lasalle County Nuclear |
350 MW | Withdrawn / abandoned |
| Gas project Y2-002, Adams County Gas |
350 MW | Withdrawn / abandoned |
| Gas project Y2-015, Schuylkill County Gas |
344 MW | Withdrawn / abandoned |
| Gas project Y2-063, Schuylkill County Gas |
344 MW | Withdrawn / abandoned |
| Panhandle Wind Onshore wind ยท Pattern Panhandle Wind, LLC |
322 MW | Withdrawn / abandoned |
| Gas project GEN-2012-016, Woodward County Gas |
312 MW | Withdrawn / abandoned |
| Prospect Energy Center Gas |
310 MW | Withdrawn / abandoned |
| Enn Mojave Power 4 Other |
300 MW | Withdrawn / abandoned |
| Solar project Q29, Clark County Solar |
300 MW | Withdrawn / abandoned |
| Route66 Wind Onshore wind ยท Route 66 LLC |
300 MW | Withdrawn / abandoned |
| Windwood Wind Onshore wind ยท Lincoln Clean |
300 MW | Withdrawn / abandoned |
| Tenaska Mountain Basin Gas |
300 MW | Withdrawn / abandoned |
| Enn Mojave Power 3 Other |
300 MW | Withdrawn / abandoned |
| Solar project Q36, San Bernardino County Solar |
300 MW | Withdrawn / abandoned |
| Boulder Solar Power Solar |
300 MW | Withdrawn / abandoned |
| Highwind Power Project Gas |
291 MW | Withdrawn / abandoned |
| Gas project 41118, Chatham County Gas ยท Duke Energy Progress, LLC |
260 MW | Withdrawn / abandoned |
| Other project X4-036 Other |
250 MW | Withdrawn / abandoned |
| Stage Coach Solar Solar + storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project GI-1216, Bon Homme County Onshore wind |
250 MW | Withdrawn / abandoned |
| Other project Y2-094 Other |
250 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-025, Ellis County Onshore wind |
250 MW | Withdrawn / abandoned |
| Sandy Valley Solar Project Solar |
250 MW | Withdrawn / abandoned |
| Enn Mojave Power 1 Other |
250 MW | Withdrawn / abandoned |
| Onshore wind project GI-1211, Williams County Onshore wind |
250 MW | Withdrawn / abandoned |
| Mirage Solar Solar |
250 MW | Withdrawn / abandoned |
| Enn Mojave Power 2 Other |
250 MW | Withdrawn / abandoned |
| Panhandle Wind 3 Onshore wind ยท PATTERN PANHANDLE WIND 3 LLC |
248 MW | Withdrawn / abandoned |
| Palmas C5 Solar |
238 MW | Withdrawn / abandoned |
| Smart Wind Ranch Onshore wind ยท Spinning Star Energy LLC |
230 MW | Withdrawn / abandoned |
| Gas project 423, Salt Lake County Gas |
230 MW | Withdrawn / abandoned |
| Gas project 40614, Chatham County Gas ยท Duke Energy Progress, LLC |
224 MW | Withdrawn / abandoned |
| Gas project 41114, Chatham County Gas ยท Duke Energy Progress, LLC |
224 MW | Withdrawn / abandoned |
| Gas project GEN-2012-042, Ford County Gas |
220 MW | Withdrawn / abandoned |
| Other project 116, Pasco County Other ยท Masked |
220 MW | Withdrawn / abandoned |
| Gas project Y2-083, Essex County Gas |
218 MW | Withdrawn / abandoned |
| Pahrump Valley Solar (Fka Lathrop Wells 240MW) Solar |
210 MW | Withdrawn / abandoned |
| Gas project Y2-065, Beaver County Gas |
205 MW | Withdrawn / abandoned |
| Gas project GEN-2012-038, Floyd County Gas |
203 MW | Withdrawn / abandoned |
| Tumbleweed Wind Farm Onshore wind ยท Tumbleweed Wind Farm, LLC |
201 MW | Withdrawn / abandoned |
| Onshore wind project J266, Roberts County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GI-2012-4, Prowers County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project 8603, Carteret County Onshore wind ยท Masked |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-018, Dixon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-030, Canadian County Onshore wind |
200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)111 ยท 19.3 GW
- CAISO (California)60 ยท 12.3 GW
- West (non-ISO utilities)95 ยท 9,460 MW
- Southeast (non-ISO utilities)36 ยท 9,047 MW
- ERCOT (Texas)24 ยท 6,711 MW
- MISO (Midcontinent)21 ยท 6,395 MW
- SPP (Southwest Power Pool)30 ยท 4,307 MW
- NYISO (New York)10 ยท 1,963 MW
- ISO-NE (New England)10 ยท 996 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)