United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
ONSHORE WIND Β· SPPOnshore wind project GEN-2012-018, Dixon County
Onshore wind project GEN-2012-018, Dixon County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Dixon County, Nebraska, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2012 (completed)
- Withdrawn / abandonedJan 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2012-018
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Tap Hoskins - Twin Church 230kV
- Location
- Dixon County, Nebraska
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 24 September 2012
- Proposed online date
- December 2014
- Withdrawn
- January 2014
Location
Marker shows the centre of Dixon County; the queue data does not give exact sites.
Other requests in Dixon County
- Onshore wind project GEN-2016-021, Dixon CountyOnshore wind Β· 299 MW Β· built
- Onshore wind project GEN-2010-051, Dixon CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project GEN-2016-116, Dixon CountyOnshore wind Β· 320 MW Β· withdrawn
- Onshore wind project GEN-2015-042, Dixon CountyOnshore wind Β· 320 MW Β· withdrawn
- Onshore wind project GEN-2008-030N, Dixon CountyOnshore wind Β· 201 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem