United States › Grid › Interconnection queues › Nebraska

ONSHORE WIND · SPP

Onshore wind project GEN-2010-051, Dixon County

Onshore wind project GEN-2010-051, Dixon County is a 200 MW onshore wind request built and operating in the SPP interconnection queue, in Dixon County, Nebraska, connecting to NPPD.

Queue statusOperating
  1. PlanningQueued Sep 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2010-051
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Wakefield 230kV
Location
Dixon County, Nebraska
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
30 September 2010
Proposed online date
December 2018
Came online
December 2018

Location

Marker shows the centre of Dixon County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Dixon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem