United States › Grid › Interconnection queues › Nebraska
ONSHORE WIND · SPPOnshore wind project GEN-2010-051, Dixon County
Onshore wind project GEN-2010-051, Dixon County is a 200 MW onshore wind request built and operating in the SPP interconnection queue, in Dixon County, Nebraska, connecting to NPPD.
Request details
- Queue ID
- GEN-2010-051
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Wakefield 230kV
- Location
- Dixon County, Nebraska
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 30 September 2010
- Proposed online date
- December 2018
- Came online
- December 2018
Location
Marker shows the centre of Dixon County; the queue data does not give exact sites.
Other requests in Dixon County
- Onshore wind project GEN-2016-021, Dixon CountyOnshore wind · 299 MW · built
- Onshore wind project GEN-2016-116, Dixon CountyOnshore wind · 320 MW · withdrawn
- Onshore wind project GEN-2015-042, Dixon CountyOnshore wind · 320 MW · withdrawn
- Onshore wind project GEN-2008-030N, Dixon CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project GEN-2012-018, Dixon CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem