United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in the USA (2019 requests) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown26427.4 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

264 requests · page 2 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Appaloosa Run Wind
Onshore wind · Appaloosa Run Wind, LLC
175 MWOperating Upton, TXERCOT Jan 20192024
Solar project J1347, Scott County
Solar
175 MWOperating Scott, MSMISO Apr 20192023
Cross Town Battery Storage
Battery storage
175 MWOperating Cumberland, MEISO-NE Apr 2019target 2025
Ratliff (Concho Valley) Solar
Solar · MERIT SI, LLC
160 MWOperating Tom Green, TXERCOT Jul 20192023
Sheep Creek Wind
Onshore wind · Century Oak Wind Project, LLC
153 MWOperating Callahan, TXERCOT May 20192023
Cottonwood Bayou Storage
Battery storage · Cottonwood Bayou Storage, LLC
153 MWOperating Brazoria, TXERCOT Oct 20192025
Bellflower Solar 1
Solar
153 MWOperating Henry, INPJM Mar 20192022
Danish Fields Storage
Battery storage · Danish Fields Storage, LLC
152 MWOperating Wharton, TXERCOT Oct 20192025
Myrtle Storage
Battery storage · Myrtle Storage, LLC
151 MWOperating Brazoria, TXERCOT Nov 20192025
Solar project J1401, Branch County
Solar
150 MWOperating Branch, MIMISO Apr 20192024
Solar project J1396, Pike County
Solar
150 MWOperating Pike, INMISO Apr 20192024
Powell Creek Solar
Solar
150 MWOperating Putnam, OHPJM Feb 20192025
Honeysuckle Solar Project
Solar
150 MWOperating St. Joseph, INPJM Sep 20192025
Elara Solar
Solar · Elara Energy Project, LLC
132 MWOperating Frio, TXERCOT Mar 20192022
Orange Grove Solar
Solar + storage · Enbridge Solar (Orange Grove), LLC
131 MWOperating Jim Wells, TXERCOT Jul 20192025
Millinocket Battery additon
Other
126 MWOperating Penobscot, MEISO-NE Apr 2019target 2020
Solar project J1205, Allen Parish County
Solar
125 MWOperating Allen Parish, LAMISO Apr 20192023
Wheatsborough Solar
Solar
125 MWOperating Erie, OHPJM Mar 20192025
Vortex BESS
Other · AZURE SKY WIND STORAGE LLC
122 MWOperating Throckmorton, TXERCOT Dec 20192023
Onshore wind project J1319, Huron County
Onshore wind
118 MWOperating Huron, MIMISO Apr 20192022
Gas project J1425, Jefferson County
Gas
114 MWOperating Jefferson, ARMISO Apr 20192022
Galloway 2 Solar
Solar · 224WB 8me LLC
114 MWOperating Concho, TXERCOT Aug 20192024
Silicon Hill Storage
Other · KCE TX 12, LLC
105 MWOperating Travis, TXERCOT Oct 20192023
Spanish Crown
Solar · BPL Crown Solar
103 MWOperating Falls, TXERCOT May 20192024
Golinda Solar
Solar · BPL Sol Solar
103 MWOperating Falls, TXERCOT Sep 20192024
Gambit Batt
Other · Gambit Energy Storage
102 MWOperating Brazoria, TXERCOT Jun 20192021
Grizzly Ridge Solar
Solar + storage · Grizzly Ridge Solar LLC
102 MWOperating Hamilton, TXERCOT Jul 20192023
Rampa
Battery storage
101 MWOperating San Bernardino, CACAISO Apr 20192024
North Fork Energy Storage
Other · North Fork Energy Storage
101 MWOperating Williamson, TXERCOT May 20192021
Bat Cave Energy Storage
Other · Bat Cave Energy Storage
101 MWOperating Mason, TXERCOT May 20192021
Eliza Storage
Other · Ables Springs Storage, LLC
100 MWOperating Kaufman, TXERCOT Dec 20192024
Pome BESS
Battery storage
100 MWOperating San Diego, CACAISO Apr 20192025
CPV Maple Hill Solar
Solar
100 MWOperating Cambria, PAPJM Mar 20192023
Solar project J1372, Pointe Coupee Parish County
Solar
100 MWOperating Pointe Coupee Parish, LAMISO Apr 20192023
Solar project 377, Lowndes County
Solar
100 MWOperating Lowndes, MSSoutheast Jun 2019target 2023
Aquilla Lake 2 Wind
Onshore wind · NextEra Energy
100 MWOperating Hill, TXERCOT May 20192023
Solar + storage project 549, Twin Falls County
Solar + storage · Franklin Solar LLC
100 MWOperating Twin Falls, IDWest Mar 20192024
Solar project J1434, Monroe County
Solar
100 MWOperating Monroe, ARMISO Apr 20192024
Clearview Solar I
Solar
99.0 MWOperating Champaign, OHPJM Mar 20192025
Anchor Wind
Onshore wind · Ranchland Wind Project,LLC
98.9 MWOperating Eastland, TXERCOT Aug 20192024
Battery storage project 61
Battery storage
95.0 MWOperating Southeast Aug 20192021
Solar project J1373, White County
Solar
95.0 MWOperating White, ARMISO Apr 20192023
Gas project 403, Morgan County
Gas
94.0 MWOperating Morgan, ALSoutheast Nov 2019target 2021
Sand Bluff Wind Repower
Onshore wind
89.5 MWOperating Glasscock, TXERCOT Nov 20192022
Odessa-Ector Unit 2 (Block 2) Uprate Repower
Gas
83.0 MWOperating Ector, TXERCOT Jun 20192022
SR Ailey
Solar
80.0 MWOperating Montgomery, GASoutheast Oct 2019target 2024
Blake Solar
Solar
80.0 MWOperating Jefferson, WVPJM Oct 20192024
Odessa-Ector Unit 1 (Block 1) Uprate
Gas · LA FRONTERA HOLDINGS LLC
80.0 MWOperating Ector, TXERCOT May 20192019
Azure Sky BESS
Other · Azure Sky Solar Project, LLC
77.6 MWOperating Haskell, TXERCOT Dec 20192022
Greensville Power Station
Gas
75.0 MWOperating Greensville, VAPJM Mar 20192023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)