πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OTHER Β· ERCOT

Azure Sky BESS

Azure Sky BESS is a 77.6 MW other request built and operating in the ERCOT interconnection queue, in Haskell County, Texas.

Queue statusOperating
  1. PlanningQueued Dec 2019 (completed)
  2. ConsentedApr 2020 (completed)
  3. Construction (completed)
  4. OperatingMay 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0476
Grid region
ERCOT (Texas)
Developer
Azure Sky Solar Project, LLC
Connection point (POI)
60515 Clear Crossing 345kV
Location
Haskell County, Texas
Technology
Other: 77.6 MW
Total requested
77.6 MW
Study phase
IA
Queue status
Operational
Entered queue
11 December 2019
Agreement signed
1 April 2020
Proposed online date
March 2022
Came online
May 2022

Location

Marker shows the centre of Haskell County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Haskell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem