United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTSand Bluff Wind Repower
Sand Bluff Wind Repower is a 89.5 MW onshore wind request built and operating in the ERCOT interconnection queue, in Glasscock County, Texas.
Request details
- Queue ID
- 20INR0296
- Grid region
- ERCOT (Texas)
- Location
- Glasscock County, Texas
- Technology
- Wind: 89.5 MW
- Total requested
- 89.5 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 26 November 2019
- Came online
- November 2022
Location
Marker shows the centre of Glasscock County; the queue data does not give exact sites.
Other requests in Glasscock County
- Gardner Draw SolarSolar · 300 MW · agreement signed
- Windjammer WindpowerOnshore wind · 293 MW · agreement signed
- Gusty WindpowerOnshore wind · 209 MW · agreement signed
- Champaign BESSBattery storage · 201 MW · agreement signed
- Honey Mesquite Wind FarmOnshore wind · 174 MW · agreement signed
- Harald (BearKat Wind B)Onshore wind · 162 MW · agreement signed
- Cannibal Draw SolarSolar + storage · 150 MW · agreement signed
- Forest Creek Wind RepowerOnshore wind · 125 MW · agreement signed
- Cannibal Draw StorageSolar + storage · 98.6 MW · agreement signed
- Proteus London-Leigh Solar SLFSolar + storage · 600 MW · in study
- Pleiades StorageBattery storage · 206 MW · in study
- Cummins BESSBattery storage · 201 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem