United States › Grid › Interconnection queues › Mississippi

SOLAR · MISO

Solar project J1347, Scott County

Solar project J1347, Scott County is a 175 MW solar request built and operating in the MISO interconnection queue, in Scott County, Mississippi, connecting to ENTERGY MISSISSIPPI.

Queue statusOperating
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedJul 2021 (completed)
  3. Construction (completed)
  4. OperatingJun 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1347
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI
Connection point (POI)
Pelahatchie - Scott 115 kV Line Tap
Location
Scott County, Mississippi
Technology
Solar: 175 MW
Total requested
175 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: In Service
Queue status
Operational
Entered queue
26 April 2019
Agreement signed
13 July 2021
Proposed online date
June 2023
Came online
June 2023

Location

Marker shows the centre of Scott County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Scott County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem