United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J1347, Scott County
Solar project J1347, Scott County is a 175 MW solar request built and operating in the MISO interconnection queue, in Scott County, Mississippi, connecting to ENTERGY MISSISSIPPI.
Request details
- Queue ID
- J1347
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY MISSISSIPPI
- Connection point (POI)
- Pelahatchie - Scott 115 kV Line Tap
- Location
- Scott County, Mississippi
- Technology
- Solar: 175 MW
- Total requested
- 175 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA Complete; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 26 April 2019
- Agreement signed
- 13 July 2021
- Proposed online date
- June 2023
- Came online
- June 2023
Location
Marker shows the centre of Scott County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Scott County
- Battery storage project J4131, Scott CountyBattery storage · 100 MW · in study
- Solar + storage project J3680, Scott CountySolar + storage · 189 MW · withdrawn
- Solar project 431, Scott CountySolar · 175 MW · withdrawn
- Gas project 230, Scott CountyGas · 150 MW · withdrawn
- Solar project J3714, Scott CountySolar · 95.0 MW · withdrawn
- Solar project IC-486, Scott CountySolar · 75.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem