United States βΊ Grid βΊ Interconnection queues βΊ Mississippi
SOLAR Β· MISOSolar project J3714, Scott County
Solar project J3714, Scott County is a 95.0 MW solar request withdrawn in the MISO interconnection queue, in Scott County, Mississippi, connecting to COOPERATIVE ENERGY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3714
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- COOPERATIVE ENERGY
- Connection point (POI)
- Homewood 69 - Lake 69.0kV
- Location
- Scott County, Mississippi
- Technology
- Solar: 95.0 MW
- Total requested
- 95.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 17 April 2024
- Proposed online date
- April 2028
- Withdrawn
- July 2025
Location
Marker shows the centre of Scott County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Scott County
- Battery storage project J4131, Scott CountyBattery storage Β· 100 MW Β· in study
- Solar project J1347, Scott CountySolar Β· 175 MW Β· built
- Solar + storage project J3680, Scott CountySolar + storage Β· 189 MW Β· withdrawn
- Solar project 431, Scott CountySolar Β· 175 MW Β· withdrawn
- Gas project 230, Scott CountyGas Β· 150 MW Β· withdrawn
- Solar project IC-486, Scott CountySolar Β· 75.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem