United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTAppaloosa Run Wind
Appaloosa Run Wind is a 175 MW onshore wind request built and operating in the ERCOT interconnection queue, in Upton County, Texas.
Request details
- Queue ID
- 20INR0249
- Grid region
- ERCOT (Texas)
- Developer
- Appaloosa Run Wind, LLC
- Connection point (POI)
- 138kV 60728 PALOUSE
- Location
- Upton County, Texas
- Technology
- Wind: 175 MW
- Total requested
- 175 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 16 January 2019
- Agreement signed
- 12 April 2021
- Proposed online date
- March 2024
- Came online
- March 2024
Location
Marker shows the centre of Upton County; the queue data does not give exact sites.
Other requests in Upton County
- McCamey's Castle BatteryBattery storage · 410 MW · agreement signed
- Larkspur Energy StorageBattery storage · 308 MW · agreement signed
- Grandfalls SolarSolar + storage · 176 MW · agreement signed
- West Royal Natural Gas (TEF-Due Diligence)Gas · 888 MW · in study
- Shadow Ranch SolarSolar · 808 MW · in study
- Tres Rios Ranch SolarSolar + storage · 508 MW · in study
- WindeckerOnshore wind · 420 MW · in study
- BRP Aras BESSBattery storage · 304 MW · in study
- Badger SolarSolar + storage · 302 MW · in study
- Vista Bluff Wind II "Alternate POI"Onshore wind · 290 MW · in study
- Vista Bluff Wind I "Alternate POI"Onshore wind · 290 MW · in study
- Tres Rios Ranch BESSSolar + storage · 290 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem