United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in PJM (Mid-Atlantic, Midwest) (2019 requests) β page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Ridgeway Solar Solar |
120 MW | Agreement signed |
| Shorebird Solar Solar |
117 MW | Paused / redesign |
| Appalachian Cottontail Solar Solar |
114 MW | Agreement signed |
| Hoodlebug Solar Energy Center Solar |
110 MW | Agreement signed |
| Rogue's Wind Onshore wind |
110 MW | Agreement signed |
| Hillandale Solar Solar Β· Hillandale Solar, LLC |
102 MW | Agreement signed |
| Bradford Solar Solar |
101 MW | Agreement signed |
| Panther Grove 2 Onshore wind |
100 MW | Agreement signed |
| Plano Skies Energy Center Solar Β· Plano Skies Energy Center, LLC |
100 MW | In study |
| Elkhart County Solar Project Solar |
100 MW | Agreement signed |
| Gibson Solar I Solar |
100 MW | Agreement signed |
| Harwood Power Battery storage |
100 MW | Agreement signed |
| Nuthatch Solar 5 Solar |
100 MW | Agreement signed |
| Rockdale Solar Solar |
100 MW | Agreement signed |
| Clermont County Solar Project Solar |
100 MW | Paused / redesign |
| Nottingham Solar Solar |
100 MW | Paused / redesign |
| Scioto Solar Solar + storage |
100 MW | Agreement signed |
| Threeforks Energy Storage Battery storage |
100 MW | Agreement signed |
| Blue Rock Solar Solar |
100 MW | Agreement signed |
| Riverstart Solar Park V Solar |
100 MW | Paused / redesign |
| Yadkins Energy Center Battery storage Β· Yadkins Energy Center, LLC |
100 MW | In study |
| Dulles Solar and BESS Solar |
100 MW | Agreement signed |
| Madison Solar 1 Solar Β· AEUG Madison Solar, LLC |
100 MW | In study |
| Bedington Energy Facility Solar |
100 MW | Paused / redesign |
| Rippon Solar |
99.0 MW | Agreement signed |
| Cassius Blue Solar Solar + storage |
94.0 MW | Agreement signed |
| Rocky Ford Solar Energy Center Solar |
90.0 MW | Paused / redesign |
| Squab Solar Solar |
90.0 MW | Agreement signed |
| Murch Solar Solar |
85.0 MW | Agreement signed |
| MPG Solar Solar |
83.6 MW | Agreement signed |
| Hawthorn Solar Solar |
83.0 MW | Agreement signed |
| Wilson Solar Solar |
80.0 MW | Agreement signed |
| Swiftwater Solar Solar |
80.0 MW | Agreement signed |
| Onshore wind project AE2-289, Allegany County Onshore wind |
80.0 MW | Agreement signed |
| MPG Solar Solar |
78.4 MW | Agreement signed |
| Hillclimber Solar Solar |
78.0 MW | Agreement signed |
| Harmony Plains Solar and Storage Facility Solar + storage |
70.0 MW | Agreement signed |
| Dixon Solar Solar |
70.0 MW | Agreement signed |
| Granite Hill Solar Solar |
70.0 MW | Paused / redesign |
| Morrow County Solar II Solar |
64.0 MW | Paused / redesign |
| Mt Olive Creek Solar Solar |
60.0 MW | Agreement signed |
| Mark Center Solar Project Solar |
60.0 MW | Agreement signed |
| Albemarle Beach Solar Solar |
60.0 MW | Agreement signed |
| Horseshoe Bend Solar Solar |
60.0 MW | Agreement signed |
| Pigeon Run Solar and Storage Solar Β· Pigeon Run Solar, LLC |
60.0 MW | Agreement signed |
| Dover Solar Facility Solar |
55.0 MW | Paused / redesign |
| Hardin Energy Center βΓΓ¬ Storage II Battery storage |
55.0 MW | Paused / redesign |
| Flat Run Solar Solar |
55.0 MW | Agreement signed |
| Dover Solar Solar |
55.0 MW | Paused / redesign |
| Gladys Solar Solar Β· Gladys Solar, LLC |
53.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)36 Β· 21.8 GW
- West (non-ISO utilities)72 Β· 21.7 GW
- MISO (Midcontinent)130 Β· 20.0 GW
- PJM (Mid-Atlantic, Midwest)183 Β· 19.2 GW
- ERCOT (Texas)72 Β· 13.4 GW
- Southeast (non-ISO utilities)37 Β· 6,006 MW
- SPP (Southwest Power Pool)21 Β· 2,722 MW
- NYISO (New York)31 Β· 2,705 MW
- ISO-NE (New England)7 Β· 1,764 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)