United States › Grid › Interconnection queues › Virginia
SOLAR · PJMRocky Ford Solar Energy Center
Rocky Ford Solar Energy Center is a 90.0 MW solar request suspended in the PJM interconnection queue, in Henry County, Virginia, connecting to AEP.
Queue statusPaused / redesign
- PlanningQueued Mar 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AE2-166
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Stockton 138 kV
- Location
- Henry County, Virginia
- Technology
- Solar: 90.0 MW
- Total requested
- 90.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 16 March 2019
- Proposed online date
- December 2026
Location
Marker shows the centre of Henry County; the queue data does not give exact sites.
Other requests in Henry County
- Henry County Solar FacilitySolar · 50.0 MW · agreement signed
- Axton SolarSolar · 201 MW · suspended
- Caden Energix AxtonSolar · 66.0 MW · built
- Smith Mountain HydroHydro · 34.0 MW · built
- Gas project AB2-145, Henry CountyGas · 572 MW · withdrawn
- Gas project AB2-146, Henry CountyGas · 382 MW · withdrawn
- Solar + storage project AG2-414, Henry CountySolar + storage · 350 MW · withdrawn
- Solar project AD2-216, Henry CountySolar · 68.0 MW · withdrawn
- Solar project AH1-175, Henry CountySolar · 20.0 MW · withdrawn
- LeatherwoodSolar · 20.0 MW · withdrawn
- Solar project AH1-176, Henry CountySolar · 18.8 MW · withdrawn
- Solar project AG1-468, Henry CountySolar · 14.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem