United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Caden Energix Axton

Caden Energix Axton is a 66.0 MW solar request built and operating in the PJM interconnection queue, in Henry County, Virginia, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingFeb 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AE1-100
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Axton 138 kV
Location
Henry County, Virginia
Technology
Solar: 66.0 MW
Total requested
66.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
3 September 2018
Proposed online date
December 2023
Came online
February 2024

Location

Marker shows the centre of Henry County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Henry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem