United States › Grid › Interconnection queues › Virginia
SOLAR · PJMCaden Energix Axton
Caden Energix Axton is a 66.0 MW solar request built and operating in the PJM interconnection queue, in Henry County, Virginia, connecting to AEP.
Request details
- Queue ID
- AE1-100
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Axton 138 kV
- Location
- Henry County, Virginia
- Technology
- Solar: 66.0 MW
- Total requested
- 66.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 3 September 2018
- Proposed online date
- December 2023
- Came online
- February 2024
Location
Marker shows the centre of Henry County; the queue data does not give exact sites.
Other requests in Henry County
- Henry County Solar FacilitySolar · 50.0 MW · agreement signed
- Axton SolarSolar · 201 MW · suspended
- Rocky Ford Solar Energy CenterSolar · 90.0 MW · suspended
- Smith Mountain HydroHydro · 34.0 MW · built
- Gas project AB2-145, Henry CountyGas · 572 MW · withdrawn
- Gas project AB2-146, Henry CountyGas · 382 MW · withdrawn
- Solar + storage project AG2-414, Henry CountySolar + storage · 350 MW · withdrawn
- Solar project AD2-216, Henry CountySolar · 68.0 MW · withdrawn
- Solar project AH1-175, Henry CountySolar · 20.0 MW · withdrawn
- LeatherwoodSolar · 20.0 MW · withdrawn
- Solar project AH1-176, Henry CountySolar · 18.8 MW · withdrawn
- Solar project AG1-468, Henry CountySolar · 14.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem