Bedington Energy Facility

Bedington Energy Facility is a 100 MW solar request suspended in the PJM interconnection queue, in Frederick County, Maryland, connecting to APS.

Queue statusPaused / redesign
  1. PlanningQueued Apr 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE2-333
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Bedington 138 kV
Location
Frederick County, Maryland
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
1 April 2019
Proposed online date
October 2025

Location

Marker shows the centre of Frederick County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Frederick County