πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

GAS Β· PJM

Gas project E05_W25, Frederick County

Gas project E05_W25, Frederick County is a 620 MW gas request withdrawn in the PJM interconnection queue, in Frederick County, Maryland, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2000 (completed)
  2. Withdrawn / abandonedNov 2002 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
E05_W25
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Doubs 500 kV or 230 kV
Location
Frederick County, Maryland
Technology
Gas: 620 MW
Total requested
620 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
4 October 2000
Proposed online date
May 2004
Withdrawn
November 2002

Location

Marker shows the centre of Frederick County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Frederick County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem