Biggs Ford Solar Facility

Biggs Ford Solar Facility is a 15.0 MW solar request built and operating in the PJM interconnection queue, in Frederick County, Maryland, connecting to APS.

Queue statusOperating
  1. PlanningQueued Oct 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB1-125
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Carroll-Monocacy 34.5kV
Location
Frederick County, Maryland
Technology
Solar: 15.0 MW
Total requested
15.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
30 October 2015
Proposed online date
September 2025
Came online
August 2025

Location

Marker shows the centre of Frederick County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Frederick County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem