Withdrawn queue requests in ISO-NE (New England) — page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown982118.1 GW
Active in queue14.6 GW72 requests
Agreement signed8,609 MW45 requests
Withdrawn982118.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

982 requests · page 14 of 20
ProjectCapacityStatusLocationRegionQueuedOnline
Battery Storage Addition
Battery storage
16.0 MWWithdrawn / abandoned New London, CTISO-NE Apr 2022target 2027
Fuel Cell
Gas
16.0 MWWithdrawn / abandoned New Haven, CTISO-NE Aug 2006target 2009
Solar
Solar
16.0 MWWithdrawn / abandoned Hillsborough, NHISO-NE Apr 2020target 2024
Battery Storage
Battery storage
16.0 MWWithdrawn / abandoned Chittenden, VTISO-NE Aug 2024target 2026
Solar
Solar
15.6 MWWithdrawn / abandoned York, MEISO-NE Oct 2023target 2024
Solar
Solar
15.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Dec 2019target 2021
Solar
Solar
15.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Nov 2018target 2021
Group @ Wing Lane 624 - EMA ASO
Solar + storage
15.0 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2022target 2023
Davenport Solar
Solar
15.0 MWWithdrawn / abandoned Rutland, VTISO-NE Apr 2018target 2021
Nellie Solar
Solar
15.0 MWWithdrawn / abandoned Sullivan, NHISO-NE Apr 2019target 2024
Solar
Solar
15.0 MWWithdrawn / abandoned Coos, NHISO-NE Oct 2018target 2020
Wind
Onshore wind
14.9 MWWithdrawn / abandoned Barnstable, MAISO-NE Dec 2010target 2012
Pratts Junc. Substation - NG WMA Group 3
Battery storage
14.9 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Lashaway Substation - NG WMA Group 3
Battery storage
14.9 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Fuel Cell
Other
14.8 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2018target 2021
Millbury substation - NG Western MA Area Cluster Study
Solar
14.4 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2023
Solar
Solar
14.0 MWWithdrawn / abandoned Cheshire, NHISO-NE Nov 2018target 2022
Battery Storage
Battery storage
14.0 MWWithdrawn / abandoned Kennebec, MEISO-NE Aug 2019target 2024
Meadow Street 552 Substation - NG WMA Group 3
Solar + storage
13.8 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Lashaway Substation - NG Western MA Area Cluster Study
Solar
13.7 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2018target 2022
Kent County - NG WRI DG Area Study #2 <5 MW
Solar
13.5 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2022
Meadow Street 552 Substation - NG Western MA Area Cluster Study
Solar
13.4 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2018target 2022
Ware Substation - NG Western MA Area Cluster Study
Solar
13.3 MWWithdrawn / abandoned Hampshire, MAISO-NE Dec 2018target 2023
West Hampden 139 substation - NG Western MA Area Cluster Study
Solar
13.2 MWWithdrawn / abandoned Hampden, MAISO-NE Mar 2019target 2023
HGE Group Study
Battery storage
13.0 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2024target 2026
MATEP - Third CTG
Gas
12.5 MWWithdrawn / abandoned Suffolk, MAISO-NE Jun 2008target 2014
Eversource Group Study @ Blandford
Solar
12.5 MWWithdrawn / abandoned Hampden, MAISO-NE Apr 2020target 2023
Barre Substation - NG WMA Group 3
Solar + storage
12.4 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Thorndike Substation - NG Western MA Area Cluster Study
Solar
12.4 MWWithdrawn / abandoned Hampden, MAISO-NE Dec 2018target 2023
Barre substation - NG Western MA Area Cluster Study
Solar
12.4 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2018target 2022
Eversource Group @ Bell Rock #661
Solar + storage
12.0 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2020target 2023
Combustion Turbine
Gas
12.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Feb 2015target 2016
Offshore Wind
Offshore wind
12.0 MWWithdrawn / abandoned Lincoln, MEISO-NE Dec 2013target 2017
Solar
Solar
12.0 MWWithdrawn / abandoned Essex, VTISO-NE Mar 2019target 2020
AWT Fitchburg Wind Project
Onshore wind
12.0 MWWithdrawn / abandoned Worcester, MAISO-NE Jun 2003target 2004
Battery Storage
Battery storage
11.9 MWWithdrawn / abandoned Franklin, MAISO-NE Sep 2022target 2027
Wind
Onshore wind
11.9 MWWithdrawn / abandoned Lincoln, MEISO-NE Nov 2011target 2017
Eversource Group @ Sandwich 916
Solar + storage
11.8 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2020target 2023
Solar
Solar
11.8 MWWithdrawn / abandoned Washington, MEISO-NE Sep 2020target 2023
Solar and Battery
Solar + storage
11.7 MWWithdrawn / abandoned York, MEISO-NE Aug 2019target 2020
Millbury Substation - NG WMA Group 3
Solar + storage
11.7 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Offshore Wind
Offshore wind
11.6 MWWithdrawn / abandoned MEISO-NE Jul 2021target 2023
Newcastle 115 kV SS - Midcoast Area DG Study
Solar
11.6 MWWithdrawn / abandoned Cumberland, MEISO-NE Oct 2023target 2024
Eversource Group Study @ Industrial Park
Solar + storage
11.3 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2020target 2023
Solar
Solar
11.0 MWWithdrawn / abandoned Newport, RIISO-NE Dec 2018target 2025
Ware Substation - NG WMA Group 3
Solar + storage
11.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Oct 2021target 2027
Adams substation - NG Western MA Area Cluster Study
Solar
11.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Mar 2019target 2021
EE Mansfield Center DG Cluster
Solar + storage
10.8 MWWithdrawn / abandoned Tolland, CTISO-NE Jan 2024target 2025
Noresco Navy
Gas
10.8 MWWithdrawn / abandoned New London, CTISO-NE May 2021target 2023
Kent County Substation - NG Western RI DG Area Study
Solar
10.4 MWWithdrawn / abandoned Kent, RIISO-NE Mar 2020target 2021
Page 14 of 20

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)