United States βΊ Grid βΊ Interconnection queues βΊ Maine
SOLAR Β· ISO-NESolar
Solar is a 11.8 MW solar request withdrawn in the ISO-NE interconnection queue, in Washington County, Maine.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedDec 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1064
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Emera Maine 34.5 kV Line 19, connecting ScottβΓΓ΄s Hill Substation and Pembroke Substation Latitude: 44.873 Longitude: -67.356
- Location
- Washington County, Maine
- Technology
- Solar: 11.8 MW
- Total requested
- 11.8 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 17 September 2020
- Proposed online date
- September 2023
- Withdrawn
- December 2020
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Downeast WindOnshore wind Β· 126 MW Β· built
- Stetson Wind II(Jimmey & Owl Mt.-UPC) See # 249Onshore wind Β· 24.0 MW Β· built
- Stetson Wind II(Jimmey & Owl Mt.-UPC)Onshore wind Β· 2.2 MW Β· built
- WindOnshore wind Β· 104 MW Β· withdrawn
- WindOnshore wind Β· 92.3 MW Β· withdrawn
- Downeast WindOnshore wind Β· 90.0 MW Β· withdrawn
- SolarSolar Β· 75.3 MW Β· withdrawn
- SolarSolar Β· 75.0 MW Β· withdrawn
- WindOnshore wind Β· 19.8 MW Β· withdrawn
- WindOnshore wind Β· 9.6 MW Β· withdrawn
- SolarSolar Β· 4.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem