United States › Grid › Interconnection queues › Maine
ONSHORE WIND · ISO-NEStetson Wind II(Jimmey & Owl Mt.-UPC) See # 249
Stetson Wind II(Jimmey & Owl Mt.-UPC) See # 249 is a 24.0 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Washington County, Maine.
Request details
- Queue ID
- 245
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- BHE Keene Road Substation
- Location
- Washington County, Maine
- Technology
- Wind: 24.0 MW
- Total requested
- 24.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 11 January 2008
- Proposed online date
- March 2010
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Downeast WindOnshore wind · 126 MW · built
- Stetson Wind II(Jimmey & Owl Mt.-UPC)Onshore wind · 2.2 MW · built
- WindOnshore wind · 104 MW · withdrawn
- WindOnshore wind · 92.3 MW · withdrawn
- Downeast WindOnshore wind · 90.0 MW · withdrawn
- SolarSolar · 75.3 MW · withdrawn
- SolarSolar · 75.0 MW · withdrawn
- WindOnshore wind · 19.8 MW · withdrawn
- SolarSolar · 11.8 MW · withdrawn
- WindOnshore wind · 9.6 MW · withdrawn
- SolarSolar · 4.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem