United States βΊ Grid βΊ Interconnection queues βΊ Maine
ONSHORE WIND Β· ISO-NEWind
Wind is a 11.9 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Lincoln County, Maine, connecting to CMP.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2011 (completed)
- Withdrawn / abandonedOct 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 381
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- CMP
- Connection point (POI)
- CMP 34.5 kV Boothbay Substation
- Location
- Lincoln County, Maine
- Technology
- Wind: 11.9 MW
- Total requested
- 11.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 14 November 2011
- Proposed online date
- September 2017
- Withdrawn
- October 2013
Location
Marker shows the centre of Lincoln County; the queue data does not give exact sites.
Other requests in Lincoln County
- Pumped Storage ProjectBattery storage Β· 1,000 MW Β· withdrawn
- Offshore WindOffshore wind Β· 12.0 MW Β· withdrawn
- Offshore WindOffshore wind Β· 10.0 MW Β· withdrawn
- Lincolnville 115 kV SS - Midcoast Area DG StudySolar Β· 4.9 MW Β· withdrawn
- Mason 115 kV SS - Midcoast Area DG StudySolar Β· 3.9 MW Β· withdrawn
- Bath 115 kV SS - Midcoast Area DG StudySolar Β· 3.4 MW Β· withdrawn
- Coopers Mills 115 kV SS - Midcoast Area DG StudySolar Β· 2.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem