Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests · page 12 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1715, Decatur County
Solar
145 MWWithdrawn / abandoned Decatur, INMISO Jun 2020target 2023
NY Kinetic Plant 1
Hydro · Hydroelectric Corporation
144 MWWithdrawn / abandoned New York, NYNYISO Jul 2020
Solar + storage project 449, Lowndes County
Solar + storage
140 MWWithdrawn / abandoned Lowndes, MSSoutheast Jul 2020
Solar project AF2-209, Defiance County
Solar · Mink Solar LLC
140 MWWithdrawn / abandoned Defiance, OHPJM Mar 2020target 2023
Solar project AG1-312, Bertie County
Solar
140 MWWithdrawn / abandoned Bertie, NCPJM Sep 2020target 2023
Solar project AG1-453, Noble County
Solar · RWE Solar Development, LLC
140 MWWithdrawn / abandoned Noble, INPJM Sep 2020target 2023
Esker Solar Park
Solar · Headwaters Wind Farm III LLC d/b/a Esker Solar Park LLC and Esker Solar Park II LLC
140 MWWithdrawn / abandoned Delaware, INPJM Mar 2020target 2023
Solar + storage project IC-878, Mitchell County
Solar + storage
135 MWWithdrawn / abandoned Mitchell, GASoutheast Jun 2020target 2023
Solar
Solar
135 MWWithdrawn / abandoned Hartford, CTISO-NE Sep 2020target 2022
Solar + storage project AF2-245, Mason County
Solar + storage
132 MWWithdrawn / abandoned Mason, KYPJM Mar 2020target 2023
Solar + storage project AF2-397, Fluvanna County
Solar + storage · Kidds Store II, LLC
130 MWWithdrawn / abandoned Fluvanna, VAPJM Apr 2020target 2023
Mainesburg ESS
Battery storage · Juno Power Management LLC
130 MWWithdrawn / abandoned Tioga, PANYISO Jun 2020
Solar project AG1-133, Spotsylvania County
Solar · Virginia Electric and Power Company
128 MWWithdrawn / abandoned Spotsylvania, VAPJM Sep 2020target 2024
Battery storage project AG1-359, City Of Chesapeake County
Battery storage · Fentress Energy Storage, LLC
128 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Sep 2020target 2024
Solar project AG1-027, City Of Suffolk County
Solar
128 MWWithdrawn / abandoned City Of Suffolk, VAPJM Jun 2020target 2024
Solar project 446, Lowndes County
Solar
127 MWWithdrawn / abandoned Lowndes, MSSoutheast Jul 2020target 2022
Bells Solar
Solar · Bells Solar, LLC
126 MWWithdrawn / abandoned Hertford, NCPJM May 2020target 2024
Solar project J1609, St. Joseph County
Solar
125 MWWithdrawn / abandoned St. Joseph, MIMISO Jun 2020target 2023
Solar + storage project AG1-490, Mercer County
Solar + storage
125 MWWithdrawn / abandoned Mercer, PAPJM Sep 2020target 2023
Solar project 453, Christian County
Solar
125 MWWithdrawn / abandoned Christian, KYSoutheast Aug 2020target 2028
Solar project 141, Richland County
Solar
125 MWWithdrawn / abandoned Richland, SCSoutheast May 2020target 2023
Solar project J1764, Perry County
Solar
125 MWWithdrawn / abandoned Perry, MOMISO Jun 2020target 2023
Solar project J1549, Clinton County
Solar
125 MWWithdrawn / abandoned Clinton, IAMISO Jun 2020target 2024
Solar project GEN-2020-022, Finney County
Solar
125 MWWithdrawn / abandoned Finney, KSSPP Apr 20202025
Solar project AF2-360, Allegany County
Solar
125 MWWithdrawn / abandoned Allegany, MDPJM Mar 2020target 2023
Solar project J1497, Jefferson County
Solar
125 MWWithdrawn / abandoned Jefferson, WIMISO Jun 2020target 2024
Hicksville Storage
Battery storage · Juno Power Management LLC
125 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2020
Other project Q336, Pinal County
Other
125 MWWithdrawn / abandoned Pinal, AZWest Mar 2020target 2021
Solar project 142, Saluda County
Solar
125 MWWithdrawn / abandoned Saluda, SCSoutheast May 2020target 2023
Solar project J1690, Henry County
Solar
125 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2023
Flowing Springs Farm
Solar + storage
125 MWWithdrawn / abandoned Jefferson, WVPJM Sep 2020target 2028
Battery storage project AG1-449, Dinwiddie County
Battery storage · RWE Solar Development, LLC
122 MWWithdrawn / abandoned Dinwiddie, VAPJM Sep 2020target 2022
Desert Vine Solar
Solar · Desert Vine Solar LLC
121 MWWithdrawn / abandoned ERCOT May 2020target 2026
Solar project 413, Putnam County
Solar
120 MWWithdrawn / abandoned Putnam, TNSoutheast Jan 2020
Solar + storage project 458, Tipton County
Solar + storage
120 MWWithdrawn / abandoned Tipton, TNSoutheast Sep 2020
Solar + storage project AG1-093, Halifax County
Solar + storage
120 MWWithdrawn / abandoned Halifax, VAPJM Jul 2020target 2023
Solar + storage project 397, Silver Bow County
Solar + storage
120 MWWithdrawn / abandoned Silver Bow, MTWest Sep 2020target 2023
Solar
Solar
120 MWWithdrawn / abandoned Penobscot, MEISO-NE May 2020target 2023
Solar + storage project IC-910, Warren County
Solar + storage
120 MWWithdrawn / abandoned Warren, GASoutheast Oct 2020target 2023
Solar project AF2-124, Highland County
Solar
120 MWWithdrawn / abandoned Highland, OHPJM Feb 2020target 2023
Solar project J1788, St. Mary Parish County
Solar
120 MWWithdrawn / abandoned St. Mary Parish, LAMISO Jun 2020target 2023
Addison Solar
Solar · SWEB Development USA LLC
120 MWWithdrawn / abandoned Steuben, NYNYISO Jul 2020
Solar + storage project AG1-497, Kent County
Solar + storage · Morgan Branch Solar I, LLC
120 MWWithdrawn / abandoned Kent, DEPJM Sep 2020target 2023
Onshore wind project TCS-11, Spokane County
Onshore wind
120 MWWithdrawn / abandoned Spokane, WAWest Mar 2020target 2023
Solar project 1203, Iron County
Solar
120 MWWithdrawn / abandoned Iron, UTWest Mar 2020target 2022
Solar + storage project AF2-391, Hardin County
Solar + storage · Naturgy Candela DevCo LLC
120 MWWithdrawn / abandoned Hardin, KYPJM Mar 2020target 2023
Battery storage project AG1-248, York County
Battery storage
119 MWWithdrawn / abandoned York, PAPJM Sep 2020target 2022
Solar project AG1-120, Dekalb County
Solar · Leeward Renewable Energy Development, LLC
119 MWWithdrawn / abandoned Dekalb, ILPJM Aug 2020target 2023
Solar project AG1-427, Mecklenburg County
Solar · ACE Development Company II, LLC
119 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2020target 2024
Solar + storage project IC-920, Jefferson County
Solar + storage
118 MWWithdrawn / abandoned Jefferson, GASoutheast Nov 2020
Page 12 of 36

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)