SOLAR Β· SPP

Solar project GEN-2020-022, Finney County

Solar project GEN-2020-022, Finney County is a 125 MW solar request withdrawn in the SPP interconnection queue, in Finney County, Kansas, connecting to SUNC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedApr 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2020-022
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Holcomb Substation 115KV
Location
Finney County, Kansas
Technology
Solar: 125 MW
Total requested
125 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 April 2020
Proposed online date
December 2025
Came online
December 2025
Withdrawn
April 2023

Location

Marker shows the centre of Finney County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Finney County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem