πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Carolina

SOLAR Β· PJM

Bells Solar

Bells Solar is a 126 MW solar request withdrawn in the PJM interconnection queue, in Hertford County, North Carolina, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2020 (completed)
  2. Withdrawn / abandonedNov 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-008
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Bells Solar, LLC
Connection point (POI)
Tunis-Mapleton 115 kV
Location
Hertford County, North Carolina
Technology
Solar: 126 MW
Total requested
126 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
1 May 2020
Proposed online date
December 2024
Withdrawn
November 2025

Location

Marker shows the centre of Hertford County; the queue data does not give exact sites.

Power plants in North Carolina Β· Transmission lines in North Carolina

Other requests in Hertford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem