United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in MISO (Midcontinent) — page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,337302.2 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,337 requests · page 12 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3464, Story County
Solar
200 MWIn study Story, IAMISO Apr 2024target 2028
Solar project J2075, Liberty County
Solar
200 MWIn study Liberty, TXMISO Aug 2021target 2028
Solar project J2002, Washington County
Solar
200 MWIn study Washington, IAMISO Aug 2021target 2024
Battery storage project J2586, Clark County
Battery storage
200 MWIn study Clark, INMISO Sep 2022target 2025
Battery storage project J4123, Branch County
Battery storage
200 MWIn study Branch, MIMISO Sep 2025target 2030
Battery storage project J3881, Clay County
Battery storage
200 MWIn study Clay, ILMISO Feb 2025target 2030
Solar project J3633, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Apr 2024target 2028
Battery storage project J3660, Rock Island County
Battery storage
200 MWIn study Rock Island, ILMISO Apr 2024target 2028
Solar project J3837, Van Buren County
Solar
200 MWIn study Van Buren, MIMISO Dec 2024target 2029
Onshore wind project J3420, Mcpherson County
Onshore wind
200 MWIn study Mcpherson, SDMISO Mar 2024target 2028
Solar project J2987, Greene County
Solar
200 MWIn study Greene, INMISO Sep 2022target 2025
Solar project J3256, Clark County
Solar
200 MWIn study Clark, ILMISO Apr 2024target 2028
Surplus; J1712
Battery storage
200 MWIn study Perry, ILMISO Apr 2025target 2027
Onshore wind project J3955, Lac Qui Parle County
Onshore wind
200 MWIn study Lac Qui Parle, MNMISO Apr 2025target 2030
Solar project J3803, Monroe County
Solar
200 MWIn study Monroe, MIMISO Apr 2024target 2028
Battery storage project J2475, Monroe County
Battery storage
200 MWIn study Monroe, MIMISO Sep 2022target 2026
Solar + storage project J4011, Miller County
Solar + storage
200 MWIn study Miller, ARMISO May 2025target 2029
Battery storage project J3703, Itasca County
Battery storage
200 MWIn study Itasca, MNMISO Mar 2024target 2028
Battery storage project J2572, Hamilton County
Battery storage
200 MWIn study Hamilton, INMISO Sep 2022target 2025
Battery storage project J2607, Montgomery County
Battery storage
200 MWIn study Montgomery, ILMISO Sep 2022target 2026
Onshore wind project J2509, Tippecanoe County
Onshore wind
200 MWIn study Tippecanoe, INMISO Sep 2022target 2025
Onshore wind project J4120, Lenawee County
Onshore wind
200 MWIn study Lenawee, MIMISO Sep 2025target 2030
Onshore wind project J1270, Palo Alto County
Onshore wind
200 MWIn study Palo Alto, IAMISO Apr 2019target 2024
Solar + storage project J1891, Attala County
Solar + storage
200 MWIn study Attala, MSMISO Aug 2021target 2027
Solar + storage project J2893, Holmes County
Solar + storage
200 MWIn study Holmes, MSMISO Sep 2022target 2027
Battery storage project J2601, Wabasha County
Battery storage
200 MWIn study Wabasha, MNMISO Sep 2022target 2026
Battery storage project J3251, Genesee County
Battery storage
200 MWIn study Genesee, MIMISO Apr 2024target 2028
Solar project J2667, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Sep 2022target 2025
Solar project J3095, Ford County
Solar
200 MWIn study Ford, ILMISO Sep 2022target 2025
Solar project J4092, Beauregard Parish County
Solar
200 MWIn study Beauregard Parish, LAMISO Oct 2025target 2030
Solar project J3287, Osceola County
Solar
200 MWIn study Osceola, MIMISO Apr 2024target 2028
Solar project J2848, Hamilton County
Solar
200 MWIn study Hamilton, INMISO Nov 2025target 2025
Onshore wind project J2577, Cross County
Onshore wind
200 MWIn study Cross, ARMISO Sep 2022target 2025
Solar + storage project J2388, Macon County
Solar + storage
200 MWIn study Macon, ILMISO Sep 2022target 2026
Solar + storage project J3979, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Solar project J2676, Huron County
Solar
200 MWIn study Huron, MIMISO Sep 2022target 2025
Solar project J2228, Concordia Parish County
Solar
200 MWIn study Concordia Parish, LAMISO Dec 2021target 2027
Solar project J2486, Monroe County
Solar
200 MWIn study Monroe, MIMISO Sep 2022target 2025
Battery storage project J1898, Olmsted County
Battery storage
200 MWIn study Olmsted, MNMISO Aug 2021target 2024
Solar project J3847, Jefferson County
Solar
200 MWIn study Jefferson, ILMISO Jan 2025target 2029
Solar project J1849, Hardin County
Solar
200 MWIn study Hardin, TXMISO Nov 2021target 2028
Battery storage project J4002, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Apr 2025target 2030
Onshore wind project J3928, Bay County
Onshore wind
200 MWIn study Bay, MIMISO Jan 2025target 2030
Onshore wind project J2938, Knox County
Onshore wind
200 MWIn study Knox, ILMISO Sep 2022target 2025
Battery storage project J3780, Buchanan County
Battery storage
200 MWIn study Buchanan, IAMISO Apr 2024target 2028
Onshore wind project J3749, Lyon County
Onshore wind
200 MWIn study Lyon, MNMISO Apr 2024target 2028
Battery storage project J2998, St. Clair County
Battery storage
200 MWIn study St. Clair, ILMISO Sep 2022target 2025
Solar project J2181, Mississippi County
Solar
200 MWIn study Mississippi, ARMISO Jul 2022target 2027
Solar project J2298, Greene County
Solar
200 MWIn study Greene, ARMISO Nov 2021target 2028
Battery storage project J3440, Daviess County
Battery storage
200 MWIn study Daviess, MOMISO Apr 2024target 2028
Page 12 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)