United States › Grid › Interconnection queues › Illinois

BATTERY STORAGE · MISO

Surplus; J1712

Surplus; J1712 is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Perry County, Illinois, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1095
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Connection point (POI)
7ASTER - 7CMDR 345.0kV
Location
Perry County, Illinois
Technology
Battery: 200 MW
Total requested
200 MW
Queue status
Active
Entered queue
22 April 2025
Proposed online date
May 2027

Location

Marker shows the centre of Perry County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Perry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem