United States › Grid › Interconnection queues › Arkansas

SOLAR + STORAGE · MISO

Solar + storage project J4011, Miller County

Solar + storage project J4011, Miller County is a 200 MW solar + storage request in interconnection study in the MISO interconnection queue, in Miller County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusIn planning
  1. PlanningQueued May 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4011
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
AECC LEWISVILLE WEST
Location
Miller County, Arkansas
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
15 May 2025
Proposed online date
August 2029

Location

Marker shows the centre of Miller County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem