Queue requests in study in the USA (2022 requests) โ€” page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,272255.2 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,272 requests ยท page 11 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project C2-131, Emery County
Solar + storage
199 MWIn study Emery, UTWest May 2022target 2026
Solar + storage project C2-115, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project C2-59, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project C2-56, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project IA-PNM-2023-06, Mckinley County
Solar + storage
199 MWIn study Mckinley, NMWest Dec 2022target 2025
Solar + storage project BHCT G33, Pueblo County
Solar + storage
199 MWIn study Pueblo, COWest Jun 2022target 2025
Solar + storage project C2-58, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2026
Solar + storage project C2-112, Utah County
Solar + storage
199 MWIn study Utah, UTWest May 2022target 2025
Solar + storage project C2-173, Lake County
Solar + storage
199 MWIn study Lake, ORWest May 2022target 2026
Battery storage project C2-171, Lake County
Battery storage
199 MWIn study Lake, ORWest May 2022target 2027
Onshore wind project GI-DISIS-2022-17, Kiowa County
Onshore wind
199 MWPaused / redesign Kiowa, COWest May 2022target 2030
Battery storage project PIS026, Utah County
Battery storage
199 MWIn study Utah, UTWest Jul 2022target 2025
Battery storage project PIS025, Utah County
Battery storage
199 MWIn study Utah, UTWest Jul 2022target 2025
Battery storage project C2-170, Lake County
Battery storage
199 MWIn study Lake, ORWest May 2022target 2026
Battery storage project J2575, Tazewell County
Battery storage
198 MWIn study Tazewell, ILMISO Sep 2022target 2027
Battery storage project J2280
Battery storage
198 MWIn study INMISO Mar 2022target 2023
Battery storage project 567168, Mecklenburg County
Battery storage
197 MWIn study Mecklenburg, NCSoutheast Jun 2022target 2029
Solar project J1948, Marion County
Solar
195 MWIn study Marion, MOMISO Mar 2022target 2024
Solar project J2334, Montgomery County
Solar
195 MWIn study Montgomery, ILMISO Sep 2022target 2027
Onshore wind project AH2-386, Pendleton County
Onshore wind
192 MWIn study Pendleton, WVPJM Mar 2022target 2027
Solar project J2136, Iroquois County
Solar
191 MWIn study Iroquois, ILMISO Mar 2022target 2024
Onshore wind project J3204, Clark County
Onshore wind
190 MWIn study Clark, WIMISO Sep 2022target 2025
Harryoung Solar
Solar + storage ยท Gransolar Texas Four LLC
190 MWIn study Cameron, TXERCOT Nov 2022target 2028
Solar project J2353, White County
Solar
190 MWIn study White, INMISO Sep 2022target 2026
Onshore wind project Company NO, Storey County
Onshore wind
190 MWPaused / redesign Storey, NVWest Mar 2022target 2026
Blanket Ranch North Solar
Solar + storage ยท Blanket Ranch North Solar, LLC
189 MWIn study Brown, TXERCOT Jun 2022target 2028
Solar project J3049, Madison County
Solar
188 MWIn study Madison, MSMISO Sep 2022target 2024
Solar project J2937, Montgomery County
Solar
186 MWIn study Montgomery, ILMISO Sep 2022target 2025
Solar project AH2-168, Madison County
Solar
185 MWIn study Madison, OHPJM Mar 2022target 2025
Maldives Solar (Oncor POI)
Solar
184 MWPaused / redesign Scurry, TXERCOT Dec 2022target 2026
Solar + storage project AI1-212, Jefferson County
Solar + storage
182 MWIn study Jefferson, PAPJM Sep 2022target 2024
Solar + storage project AH2-153, Vermillion County
Solar + storage
180 MWIn study Vermillion, INPJM Feb 2022target 2024
Onshore wind project J2965, Morehouse Parish County
Onshore wind
180 MWIn study Morehouse Parish, LAMISO Sep 2022target 2025
Solar + storage project AH2-373, Berrien County
Solar + storage
180 MWIn study Berrien, MIPJM Mar 2022target 2028
Battery storage project AH2-423, Calvert County
Battery storage
180 MWIn study Calvert, MDPJM Mar 2022target 2025
Solar project J2656, Macon County
Solar
180 MWIn study Macon, ILMISO Sep 2022target 2026
Solar + storage project J3003, Mason County
Solar + storage
180 MWIn study Mason, ILMISO Sep 2022target 2025
Onshore wind project J2654, Clinton County
Onshore wind
180 MWIn study Clinton, INMISO Sep 2022target 2026
Solar project GEN-2022-038, Harrison County
Solar
180 MWIn study Harrison, TXSPP Jun 2022target 2029
Solar project J3167, Fulton County
Solar
180 MWIn study Fulton, ILMISO Sep 2022target 2026
Solar project J2578, Tuscola County
Solar
180 MWIn study Tuscola, MIMISO Sep 2022target 2026
Solar project J2847, Starke County
Solar
180 MWIn study Starke, INMISO Sep 2022target 2026
Onshore wind project J2247, Marshall County
Onshore wind
178 MWIn study Marshall, ILMISO Mar 2022target 2024
Onshore wind project J2571, Tunica County
Onshore wind
177 MWIn study Tunica, MSMISO Sep 2022target 2024
Solar project GEN-2022-075, Ellis County
Solar
175 MWIn study Ellis, KSSPP Sep 2022target 2027
Solar project J3059, Midland County
Solar
175 MWIn study Midland, MIMISO Sep 2022target 2026
Solar project J2258, Adams County
Solar
175 MWIn study Adams, ILMISO Mar 2022target 2024
Solar project J2876, Arenac County
Solar
175 MWIn study Arenac, MIMISO Sep 2022target 2025
Battery storage project 146, Pima County
Battery storage
175 MWIn study Pima, AZWest Dec 2022target 2026
Onshore wind project J2437, Lee County
Onshore wind
175 MWIn study Lee, ARMISO Sep 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)