ONSHORE WIND · WEST

Onshore wind project GI-DISIS-2022-17, Kiowa County

Onshore wind project GI-DISIS-2022-17, Kiowa County is a 199 MW onshore wind request suspended in the West interconnection queue, in Kiowa County, Colorado, connecting to Tri-State Generation and Transmission Association.

Queue statusPaused / redesign
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-DISIS-2022-17
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Towner 230kV Switching Station
Location
Kiowa County, Colorado
Technology
Wind: 199 MW
Total requested
199 MW
Service type
Energy only (ERIS)
Study phase
Suspended LGIA
Queue status
Suspended
Entered queue
27 May 2022
Proposed online date
May 2030

Location

Marker shows the centre of Kiowa County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Kiowa County