United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA (2023 requests) — page 10
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Antlia Battery storage |
205 MW | In study |
| Saguaro Energy Storage Battery storage |
205 MW | In study |
| Mt Baldy Energy Storage 2 Battery storage |
205 MW | In study |
| Reynolds Park BESS Battery storage |
205 MW | Paused / redesign |
| Guitar BESS Battery storage · Guitar BESS LLC |
205 MW | In study |
| Southern Select Energy Storage Battery storage · SOUTHERN SELECT ENERGY STORAGE LLC |
205 MW | Agreement signed |
| Running Iron Solar Solar · Running Iron Solar, LLC |
205 MW | In study |
| Container Solar |
205 MW | In study |
| Grapevine 1 Solar |
205 MW | In study |
| Nelson Hills Solar |
205 MW | In study |
| Arc Energy Storage Battery storage · Paris Energy Storage, LLC |
205 MW | In study |
| Charro Creek Solar 1 SLF Solar + storage · Charro Creek Solar LLC |
203 MW | In study |
| Bigway Solar II Solar · NextEra Energy Interconnection Holdings, LLC |
203 MW | Agreement signed |
| Charro Creek Solar 2 SLF Solar + storage · Charro Creek Solar LLC |
203 MW | In study |
| Charro Creek Solar 3 SLF Solar + storage · Charro Creek Solar LLC |
203 MW | In study |
| Gas project GEN-2022-147, Hale County Gas |
203 MW | In study |
| Crowded Star I BESS Solar + storage · Jones City Solar II, LLC |
203 MW | Agreement signed |
| Elan BESS Battery storage · Elan BESS, LLC |
203 MW | In study |
| Brundage Energy Storage Battery storage |
202 MW | In study |
| Willow Beach Wind Onshore wind · Capital Wind, LLC |
202 MW | Agreement signed |
| Solar + storage project G0945, Fremont County Solar + storage |
202 MW | In study |
| Thomas Cameron BESS Battery storage · Thomas Cameron BESS LLC |
202 MW | Agreement signed |
| Exodus BESS Battery storage · Exodus Solar LLC |
201 MW | In study |
| El Molino Solar SLF Solar + storage · El Molino Solar, LLC |
201 MW | In study |
| Rush ESS Battery storage · OCI Solar Power LLC |
201 MW | In study |
| Nockenut Springs Solar 5 Solar · Pecan Springs Energy, LLC |
201 MW | In study |
| Echols Grove, LLC Solar · Echols Grove, LLC |
201 MW | Agreement signed |
| Savannah Oaks Solar Solar · Savannah Oaks Solar Project LLC |
201 MW | In study |
| Dios BESS Battery storage · Dios BESS, LLC |
201 MW | Agreement signed |
| Marcus Energy Storage Battery storage · Marcus Energy Storage, LLC |
201 MW | In study |
| Copano Bay Energy Storage Battery storage · Copano Bay Energy Storage, LLC |
201 MW | In study |
| Timberline Solar Solar + storage · Timberline Renewables, LLC |
201 MW | In study |
| Felix West Solar Solar + storage · Felix 1, LLC |
201 MW | Agreement signed |
| Castle Corral BESS Battery storage |
201 MW | Paused / redesign |
| Felix East Solar Solar + storage · Felix 1, LLC |
201 MW | Agreement signed |
| Cottontail Energy Center Battery storage · Cottontail Energy Center, LLC |
201 MW | In study |
| Kahla Storage Battery storage · BT Kahla Storage, LLC |
201 MW | In study |
| Bell Creek BESS Battery storage · BELL CREEK BESS, LLC |
201 MW | Agreement signed |
| Fike BESS Battery storage · BRP Blue Topaz 9, LLC |
201 MW | In study |
| Pecos Storage Center Wind + storage · Laurel Energy Center, LLC |
201 MW | Agreement signed |
| Falcon Zapata Storage 138 Battery storage · Falcon BESS, LLC |
201 MW | In study |
| Augie BESS Battery storage · BRP Blue Topaz 5, LLC |
201 MW | In study |
| Blanquilla BESS Battery storage · Blanquilla BESS LLC |
201 MW | Agreement signed |
| Bobcat Cameron BESS Battery storage · Bobcat BESS, LLC |
201 MW | In study |
| Longday Solar SLF Solar + storage · Longday Solar |
201 MW | In study |
| Eagle Claw Energy Center Battery storage · Eagle Claw Energy Center, LLC |
201 MW | Agreement signed |
| Stinger Energy Storage Battery storage · Stinger Energy Storage LLC |
201 MW | In study |
| Anila Solar Solar + storage · Alina Energy LLC |
201 MW | Agreement signed |
| Beitel Energy Storage Battery storage · Brazos Energy Storage, LLC |
201 MW | In study |
| Red Top Solar I Solar · Cat Red Top Solar, LLC |
201 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)309 · 110.9 GW
- ERCOT (Texas)356 · 76.0 GW
- CAISO (California)107 · 53.4 GW
- Southeast (non-ISO utilities)210 · 24.0 GW
- SPP (Southwest Power Pool)82 · 15.1 GW
- PJM (Mid-Atlantic, Midwest)156 · 14.6 GW
- MISO (Midcontinent)23 · 3,679 MW
- ISO-NE (New England)6 · 1,053 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)