United States › Grid › Interconnection queues › Idaho
SOLAR + STORAGE · WESTSolar + storage project G0945, Fremont County
Solar + storage project G0945, Fremont County is a 202 MW solar + storage request in interconnection study in the West interconnection queue, in Fremont County, Idaho.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- G0945
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Goshen-Drummond No 1 161kV line
- Location
- Fremont County, Idaho
- Technology
- Solar: 150 MW · Battery: 52.0 MW
- Total requested
- 202 MW
- Service type
- NRIS and ERIS
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 4 October 2023
- Proposed online date
- June 2026
Location
Marker shows the centre of Fremont County; the queue data does not give exact sites.
Other requests in Fremont County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem