SOLAR Β· WESTSolar project G1033, Fremont County
Solar project G1033, Fremont County is a 170 MW solar request withdrawn in the West interconnection queue, in Fremont County, Idaho.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G1033
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Targhee-Drummond No 1 115 kV line
- Location
- Fremont County, Idaho
- Technology
- Solar: 170 MW
- Total requested
- 170 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 21 November 2023
- Proposed online date
- October 2028
Location
Marker shows the centre of Fremont County; the queue data does not give exact sites.
Other requests in Fremont County
- Solar + storage project G0945, Fremont CountySolar + storage Β· 202 MW Β· in study
- Other project FLRV, Fremont CountyOther Β· 9.1 MW Β· built
- Hydro project 344, Fremont CountyHydro Β· 3.6 MW Β· withdrawn
- Hydro project TCS-49, Fremont CountyHydro Β· 1.8 MW Β· withdrawn
- Hydro project 1182, Fremont CountyHydro Β· 1.8 MW Β· withdrawn