🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Minnesota — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown48280.5 GW
Active in queue28.4 GW155 requests
Agreement signed309 MW9 requests
Withdrawn48280.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

482 requests · page 10 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G430, Pope County
Onshore wind
8.3 MWWithdrawn / abandoned Pope, MNMISO May 2004target 2005
Solar project GEN-2017-103, Chippewa County
Solar
8.0 MWWithdrawn / abandoned Chippewa, MNSPP May 2017target 2018
Onshore wind project G585, Redwood County
Onshore wind
8.0 MWWithdrawn / abandoned Redwood, MNMISO Dec 2005target 2008
Onshore wind project G394, Lincoln County
Onshore wind
6.6 MWWithdrawn / abandoned Lincoln, MNMISO Jan 2004target 2005
Onshore wind project G603, Lincoln County
Onshore wind
6.3 MWWithdrawn / abandoned Lincoln, MNMISO Feb 2006target 2009
Onshore wind project G516, Nobles County
Onshore wind
6.0 MWWithdrawn / abandoned Nobles, MNMISO Apr 2005target 2006
Onshore wind project G608, Pope County
Onshore wind
6.0 MWWithdrawn / abandoned Pope, MNMISO Mar 2006target 2006
Onshore wind project G817, Grant County
Onshore wind
5.9 MWWithdrawn / abandoned Grant, MNMISO Jul 2007
Onshore wind project G778, Grant County
Onshore wind
5.9 MWWithdrawn / abandoned Grant, MNMISO Mar 2007target 2009
Other project G400, Mcleod County
Other
5.0 MWWithdrawn / abandoned Mcleod, MNMISO Jan 2004target 2004
Onshore wind project J035, Wilkin County
Onshore wind
4.9 MWWithdrawn / abandoned Wilkin, MNMISO Mar 2009target 2010
Onshore wind project G395, Lincoln County
Onshore wind
4.9 MWWithdrawn / abandoned Lincoln, MNMISO Jan 2004target 2004
Onshore wind project J033, Cottonwood County
Onshore wind
4.9 MWWithdrawn / abandoned Cottonwood, MNMISO Mar 2009target 2010
Onshore wind project J032, Watonwan County
Onshore wind
4.9 MWWithdrawn / abandoned Watonwan, MNMISO Mar 2009target 2010
Onshore wind project J155, Lyon County
Onshore wind
4.9 MWWithdrawn / abandoned Lyon, MNMISO Jun 2010target 2012
Onshore wind project J058, Cottonwood County
Onshore wind
4.9 MWWithdrawn / abandoned Cottonwood, MNMISO Jul 2009target 2011
Onshore wind project J036, Jackson County
Onshore wind
4.9 MWWithdrawn / abandoned Jackson, MNMISO Mar 2009target 2010
Onshore wind project J148, Olmsted County
Onshore wind
4.9 MWWithdrawn / abandoned Olmsted, MNMISO Jun 2010target 2011
Onshore wind project J126, Winona County
Onshore wind
4.9 MWWithdrawn / abandoned Winona, MNMISO Apr 2010target 2012
Other project G279, Lincoln County
Other
4.0 MWWithdrawn / abandoned Lincoln, MNMISO Dec 2002target 2005
Other project G280, Lincoln County
Other
4.0 MWWithdrawn / abandoned Lincoln, MNMISO Dec 2002target 2003
Onshore wind project G846, Clay County
Onshore wind
4.0 MWWithdrawn / abandoned Clay, MNMISO Aug 2007target 2011
Onshore wind project GI-0914, Lyon County
Onshore wind
3.6 MWWithdrawn / abandoned Lyon, MNWest May 2009target 2010
Onshore wind project G402, Lincoln County
Onshore wind
3.3 MWWithdrawn / abandoned Lincoln, MNMISO Feb 2004target 2005
Onshore wind project G584, Pipestone County
Onshore wind
3.0 MWWithdrawn / abandoned Pipestone, MNMISO Dec 2005target 2007
Onshore wind project G729, Otter Tail County
Onshore wind
2.5 MWWithdrawn / abandoned Otter Tail, MNMISO Jan 2007target 2009
Other project J916, Cottonwood County
Other
2.0 MWWithdrawn / abandoned Cottonwood, MNMISO Jun 2017target 2020
Onshore wind project G097, Murray County
Onshore wind
2.0 MWWithdrawn / abandoned Murray, MNMISO Jun 2001
Other project G123, Murray County
Other
2.0 MWWithdrawn / abandoned Murray, MNMISO Sep 2001target 2003
Onshore wind project G372, Pope County
Onshore wind
1.7 MWWithdrawn / abandoned Pope, MNMISO Nov 2003target 2009
Onshore wind project G596, Morrison County
Onshore wind
1.0 MWWithdrawn / abandoned Morrison, MNMISO Feb 2006target 2009
Other project G124, Murray County
Other
1.0 MWWithdrawn / abandoned Murray, MNMISO Sep 2001target 2005
Page 10 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)