United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project G608, Pope County
Onshore wind project G608, Pope County is a 6.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Pope County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2006 (completed)
- Withdrawn / abandonedAug 2011 (project stopped here)
- ConsentedAug 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G608
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- GRE Lake Johanna - Brooten 69 kV
- Location
- Pope County, Minnesota
- Technology
- Wind: 6.0 MW
- Total requested
- 6.0 MW
- Study phase
- DPP - SIS
- Queue status
- Withdrawn
- Entered queue
- 2 March 2006
- Agreement signed
- 18 August 2011
- Proposed online date
- November 2006
- Withdrawn
- August 2011
Location
Marker shows the centre of Pope County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Pope County
- Onshore wind project G657, Pope CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project G658, Pope CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project G549, Pope CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project G812, Pope CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project G789, Pope CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project G365, Pope CountyOnshore wind Β· 11.0 MW Β· withdrawn
- Onshore wind project G430, Pope CountyOnshore wind Β· 8.3 MW Β· withdrawn
- Onshore wind project G372, Pope CountyOnshore wind Β· 1.7 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem