ONSHORE WIND Β· MISO

Onshore wind project G549, Pope County

Onshore wind project G549, Pope County is a 20.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Pope County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2005 (completed)
  2. Withdrawn / abandonedJun 2018 (project stopped here)
  3. ConsentedMar 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G549
Grid region
MISO (Midcontinent)
Connection point (POI)
Next to Williams Substation (69 kV)
Location
Pope County, Minnesota
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
21 September 2005
Agreement signed
13 March 2012
Proposed online date
December 2008
Withdrawn
June 2018

Location

Marker shows the centre of Pope County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Pope County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem