ONSHORE WIND Β· MISO

Onshore wind project G789, Pope County

Onshore wind project G789, Pope County is a 20.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Pope County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2007 (completed)
  2. Withdrawn / abandonedDec 2011 (project stopped here)
  3. ConsentedDec 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G789
Grid region
MISO (Midcontinent)
Connection point (POI)
T-126-N, R-36-W
Location
Pope County, Minnesota
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
25 April 2007
Agreement signed
30 December 2011
Proposed online date
September 2010
Withdrawn
December 2011

Location

Marker shows the centre of Pope County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Pope County