Onshore wind project G812, Pope County

Onshore wind project G812, Pope County is a 20.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Pope County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2007 (completed)
  2. Withdrawn / abandonedApr 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G812
Grid region
MISO (Midcontinent)
Connection point (POI)
GRE Swift Falls - Gilchrest 69kV
Location
Pope County, Minnesota
Technology
Wind: 20.0 MW
Total requested
20.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
21 June 2007
Withdrawn
April 2015

Location

Marker shows the centre of Pope County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Pope County