πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G778, Grant County

Onshore wind project G778, Grant County is a 5.9 MW onshore wind request withdrawn in the MISO interconnection queue, in Grant County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2007 (completed)
  2. Withdrawn / abandonedJan 2013 (project stopped here)
  3. ConsentedJan 2013 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G778
Grid region
MISO (Midcontinent)
Connection point (POI)
OTP Nashua Tintah - Wendell 41.6kV
Location
Grant County, Minnesota
Technology
Wind: 5.9 MW
Total requested
5.9 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
29 March 2007
Agreement signed
24 January 2013
Proposed online date
January 2009
Withdrawn
January 2013

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem