United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
SOLAR Β· SPPSolar project GEN-2017-103, Chippewa County
Solar project GEN-2017-103, Chippewa County is a 8.0 MW solar request withdrawn in the SPP interconnection queue, in Chippewa County, Minnesota, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2017 (completed)
- Withdrawn / abandonedFeb 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-103
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Granite Falls 230kV Substation
- Location
- Chippewa County, Minnesota
- Technology
- Solar: 8.0 MW
- Total requested
- 8.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 20 May 2017
- Proposed online date
- October 2018
- Withdrawn
- February 2018
Location
Marker shows the centre of Chippewa County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Chippewa County
- Replacing 258MW ERIS gas/oil with 237MW ERIS Natural Gas/oil; Wheaton 1-4Gas Β· 237 MW Β· in study
- Onshore wind project GEN-2016-036, Chippewa CountyOnshore wind Β· 44.6 MW Β· built
- Solar project J1647, Chippewa CountySolar Β· 150 MW Β· withdrawn
- Battery storage project J1693, Chippewa CountyBattery storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem