ONSHORE WIND Β· MISO

Onshore wind project G585, Redwood County

Onshore wind project G585, Redwood County is a 8.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Redwood County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2005 (completed)
  2. Withdrawn / abandonedMar 2006 (project stopped here)
  3. ConsentedMar 2006 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G585
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Redwood County, Minnesota
Technology
Wind: 8.0 MW
Total requested
8.0 MW
Queue status
Withdrawn
Entered queue
30 December 2005
Agreement signed
24 March 2006
Proposed online date
June 2008
Withdrawn
March 2006

Location

Marker shows the centre of Redwood County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Redwood County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem