Onshore wind project J126, Winona County is a 4.9 MW onshore wind request withdrawn in the MISO interconnection queue, in Winona County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2010 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J126
Grid region
MISO (Midcontinent)
Connection point (POI)
ITC Midwest Rushford - Wilson 69kV
Location
Winona County, Minnesota
Technology
Wind: 4.9 MW
Total requested
4.9 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
23 April 2010
Agreement signed
20 July 2012
Proposed online date
October 2012
Withdrawn
July 2012

Location

Marker shows the centre of Winona County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Winona County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem