ONSHORE WIND Β· MISO

Onshore wind project J033, Cottonwood County

Onshore wind project J033, Cottonwood County is a 4.9 MW onshore wind request withdrawn in the MISO interconnection queue, in Cottonwood County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedFeb 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J033
Grid region
MISO (Midcontinent)
Connection point (POI)
1 pole north of sub, Alliant 69 kV line
Location
Cottonwood County, Minnesota
Technology
Wind: 4.9 MW
Total requested
4.9 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
11 March 2009
Agreement signed
8 February 2011
Proposed online date
September 2010

Location

Marker shows the centre of Cottonwood County; the queue data does not give exact sites.